March 2024 Quarterly Activities & Cash Flow Reports
Released
Released
Announcement PDF
ASX RELEASE
30 APRIL 2024
QUARTERLY ACTIVITIES REPORT MARCH 2024
HIGHLIGHTS
• Completion of 17 hole 5,534m Phase 2 RC drilling program at Mulga Tank Ni-Cu-PGE Project
• Modelling of JORC Exploration Target for shallow, potentially open-pitable, nickel sulphide
mineralisation within the main body of the Complex 350Mt to 2,200Mt at 0.24% to 0.35% Ni
• Commencement of deep diamond hole MTD029 (EIS3) testing basal MobileMT target
• Phase 2 RC assay results received showing broad ~200m zones of nickel sulphide mineralisation
within the top ~300m including:
MTRC024
199m at 0.31% Ni, 148ppm Co, 76ppm Cu, 23ppb Pt+Pd from 161m with S:Ni 1.1
MTRC034
240m at 0.30% Ni, 133ppm Co, 133ppm Cu, 36ppb Pt+Pd from 90m with S:Ni 1.0
MTRC038
199m at 0.31% Ni, 139ppm Co, 260ppm Cu, 27ppb Pt+Pd from 119m with S:Ni 1.3
• Multiple zones of higher grade matrix to semi-massive sulphide encountered in RC drilling
including:
MTRC018
1m at 1.84% Ni, 0.10% Co, 4.88% Cu, 26ppb Pt+Pd from 293m
MTRC024
3m at 2.19% Ni, 777ppm Co, 597ppm Cu, 9ppb Pt+Pd from 253m
inc. 1m at 4.51% Ni, 0.16% Co, 0.14% Cu, 16ppb Pt+Pd from 253m
MTRC032
6m at 1.01% Ni, 443ppm Co, 0.32% Cu, 0.12g/t Pt+Pd from 254m
MTRC038
2m at 1.51% Ni, 539ppm Co, 0.72% Cu, 94ppb Pt+Pd from 135m
1m at 3.16% Ni, 662ppm Co, 385ppm Cu, 0.18g/t Pt+Pd from 192m
• WMG continues to de-risk a potentially globally significant, large-scale, open-pitable nickel
sulphide deposit at Mulga Tank
• Review, site visits and fieldwork at a number of the Company’s gold exploration projects noting
the current high gold price
• Capital raise of $1,052,495 during the period to further support exploration at Mulga Tank
Western Mines Group Ltd (WMG or Company) (ASX:WMG) is pleased to provide shareholders with the following
Quarterly Activities Report, and accompanying Appendix 5B, for what has been another extremely productive
quarter for the Company.
WMG’s main focus for the period continued to be the flagship Mulga Tank Ni-Cu-PGE Project where results
further validate the discovery of a major nickel sulphide mineral system.
Western Mines Group Ltd
Level 3, 33 Ord Street
West Perth WA 6005
ASX:WMG
Telephone: +61 475 116 798
Email: contact@westernmines.com.au
www.westernmines.com.au
Shares on Issue: 75.08m
Share Price: $0.44
Market Cap: $33.04m
Cash: $1.77m (31/03/24)
1
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
Final assay results from the initial Phase 1 22 hole reverse circulation (RC) drilling program were received at the
beginning of the quarter and further confirmed extensive shallow disseminated nickel sulphide mineralisation
within the main body of the Complex (ASX, First RC Assays Show Broad Zones of Mineralisation, 14 November
2023; MTRC009 Assays Confirm 367m of Nickel Mineralisation, 30 November 2023; MTRC015 Assays Reveal
Multiple Intersections Over 1% Ni, 4 December 2023; MTRC018 Assays Confirm Massive Sulphide 1.8% Ni,
4.9% Cu, 6 December 2023; First RC Without Mineralisation Found at Mulga Tank, 21 December 2023; More
Intersections over 1% Ni at Mulga Tank, 11 January 2024).
Modelling of 2023 diamond and Phase 1 RC results identified a significant shallow mineralised zone, which has
been reported as an Exploration Target, in according with JORC 2012 (ASX, Mulga Tank JORC Exploration
Target, 5 February 2024). The Company’s internal modelling work was reviewed by independent consultants
CSA Global. The Exploration Target with an estimated range of potential mineralisation is:
350 to 2,200 million tonnes grading 0.24% to 0.35% Ni, 120 to 150ppm Co with S:Ni 1.1 to 1.3
During the quarter the Company completed a further 17 hole, 5,534m hole (RC) drilling program. The Phase 2
RC drilling was focused on infilling the higher grade core of the Exploration Target and extending the shallow
mineralisation to the south of the Phase 1 area (ASX, 2024 Exploration Programs Commence at Mulga Tank, 29
January 2024; Completion of Phase 2 RC Drilling Commencement of EIS3, 8 April 2024).
Assay results from 13 of the 17 holes in the Phase 2 program were received during the period, with extensive
intervals of nickel sulphide mineralisation observed in all of the holes. A number of the holes returned broad
intersections of mineralisation over greater than 200m length, similar to Phase 1 hole MTRC016, including:
MTRC024
199m at 0.31% Ni, 148ppm Co, 76ppm Cu, 23ppb Pt+Pd from 161m S:Ni 1.1*
MTRC026
226m at 0.28% Ni, 125ppm Co, 62ppm Cu, 15ppb Pt+Pd from 86m S:Ni 0.7
MTRC031
210m at 0.28% Ni, 137ppm Co, 104ppm Cu, 24ppb Pt+Pd from 87m S:Ni 1.2
MTRC032
198m at 0.28% Ni, 145ppm Co, 249ppm Cu, 28ppb Pt+Pd from 108m S:Ni 1.6*
MTRC034
240m at 0.30% Ni, 133ppm Co, 133ppm Cu, 36ppb Pt+Pd from 90m S:Ni 1.0*
MTRC038
199m at 0.31% Ni, 139ppm Co, 260ppm Cu, 27ppb Pt+Pd from 119m S:Ni 1.3*
* Ending in mineralisation
Broad intersections of visible disseminated nickel sulphide mineralisation, grading up to semi-massive in some
intersections, were observed and logged in the Phase 2 RC program (ASX, Semi-Massive Sulphide in Mulga
Tank Phase 2 RC Holes, 29 February 2024). These observations were confirmed by assay results with a number
of the holes returning higher grade assay results between 1% to 4.5% Ni. Relatively shallow higher grade results
within the central core area of the Mulga Tank Complex include:
MTRC015
1m at 1.11% Ni, 379ppm Co, 0.45% Cu, 62ppb Pt+Pd from 172m
3m at 1.32% Ni, 516ppm Co, 0.10% Cu, 34ppb Pt+Pd from 184m
2m at 1.71% Ni, 836ppm Co, 0.10% Cu, 0.4g/t Pt+Pd from 229m
MTRC018
1m at 1.84% Ni, 0.10% Co, 4.88% Cu, 26ppb Pt+Pd from 293m
MTRC024
1m at 1.28% Ni, 890ppm Co, 427ppm Cu, 37ppb Pt+Pd from 202m
3m at 2.19% Ni, 777ppm Co, 597ppm Cu, 9ppb Pt+Pd from 253m
inc. 1m at 4.51% Ni, 0.16% Co, 0.14% Cu, 16ppb Pt+Pd from 253m
ASX:WMG
www.westernmines.com.au
2
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
MTRC032
1m at 1.08% Ni, 602ppm Co, 379ppm Cu, 83ppb Pt+Pd from 131m
6m at 1.01% Ni, 443ppm Co, 0.32% Cu, 0.12g/t Pt+Pd from 254m
MTRC032
2m at 1.51% Ni, 539ppm Co, 0.72% Cu, 94ppb Pt+Pd from 135m
1m at 3.16% Ni, 662ppm Co, 385ppm Cu, 0.18g/t Pt+Pd from 192m
Following the Phase 2 RC program the Company recommenced diamond drilling at the project with EIS cofunded deep diamond hole MTD029 (EIS3) (ASX, Completion of Phase 2 RC Drilling Commencement of EIS3, 8
April 2024; WMG Wins $220,000 EIS Award to Drill Mulga Tank, 19 October 2023).
During March the Company successfully completed a capital raise of $1,052,495 (before costs) through the
issue of 7,016,636 new fully paid ordinary shares at an issue price of $0.15 per share in order to support
ongoing exploration at Mulga Tank (ASX, Capital Raise to Further Progress Mulga Tank, 13 March 2024).
The Company notes the recent increase in the gold price and undertook desktop reviews, sites visits and
fieldwork at a number of the Company’s gold projects during the period.
PROJECT OVERVIEW
Figure 1: Map of WMG project locations
ASX:WMG
www.westernmines.com.au
3
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
MULGA TANK
The Mulga Tank Project comprises exploration licences E39/2132, E39/2134 and E39/2223 and exploration
licence application E39/2299, covering the Minigwal Greenstone Belt, 190km east-northeast of Kalgoorlie. The
Minigwal Greenstone Belt is a NNW trending linear sequence of predominantly mafic and ultramafic lithologies; it
is very under explored due to the presence of shallow sand cover and presents a “frontier” exploration
opportunity for major Ni-Cu-PGE and orogenic gold deposits.
Exploration results from the Company’s various drilling programs at the Mulga Tank Project over the last 12
months have demonstrated significant nickel sulphide mineralisation and an extensive nickel sulphide mineral
system within the Mulga Tank Ultramafic Complex (ASX, MTD023 Assays Confirm Discovery of Significant Nickel
Sulphide System, 5 April 2023; MTD026 Assays - 840m of Nickel Sulphide Mineralisation, 30 August 2023;
MTD027 Expands Mineralisation 4km Across Mulga Tank, 28 August 2023).
WMG recently completed a 17 hole 5,534m Phase 2 RC drilling program and has recommenced diamond
drilling at the project (ASX, Completion of Phase 2 RC Drilling Commencement of EIS3, 8 April 2024). This two
pronged approach uses RC to infill and prove up the extent of shallow disseminated nickel sulphide
mineralisation, defined by the Company’s JORC Exploration Target modelling (ASX, Mulga Tank JORC
Exploration Target, 5 February 2024), whilst the diamond drilling program continues to test deeper targets.
Further drill holes will continue to be added to these programs, with ongoing targeting work, as the Company
systematically explores the Mulga Tank Ultramafic Complex.
RC DRILLING PROGRAMS
During the previous quarter the Company completed a 22 hole reverse circulation (RC) drilling program. This
was the first drilling designed to systematically test the lateral continuity of the shallow, uppermost zone of
disseminated nickel sulphide mineralisation observed in the Company’s diamond holes MTD012, MTD022,
MTD023, MTD026, MTD027 and MTD028 within the main body of the Mulga Tank Ultramafic Complex (ASX,
RC Drilling Program Commences at Mulga Tank, 20 September 2023; RC Drilling Expansion and Drilling for
Equity, 17 October 2023; Completion of 7000m RC Drilling Program at Mulga Tank, 7 November 2023).
The holes were spaced at approximately 500m x 300m and covered a 2,500m x 1,000m area across the centre
of the Complex. Each hole was designed to a target depth of ~300m, which was achieved in all but three holes,
for a total of 7,035.5m - of which the top ~60m of each hole, or 1,321m in total, was mud-rotary drilling through
the sand cover.
Final geochemical assay results were received for this program at the beginning of the period (ASX, First RC
Assays Show Broad Zones of Mineralisation, 14 November 2023; MTRC009 Assays Confirm 367m of Nickel
Mineralisation, 30 November 2023; MTRC015 Assays Reveal Multiple Intersections Over 1% Ni, 4 December
2023; MTRC018 Assays Confirm Massive Sulphide 1.8% Ni, 4.9% Cu, 6 December 2023; First RC Without
Mineralisation Found at Mulga Tank, 21 December 2023; More Intersections over 1% Ni at Mulga Tank, 11
January 2024). Of these 22 holes, 19 holes demonstrate significant evidence for “live” magmatic sulphide
chemical processes and nickel sulphide mineralisation.
Zones of mineralisation were generally defined by a combination of the various geochemical indicators and cutoff grades (Ni >0.16%, Cu >20ppm, Pt+Pd >20ppb, S >0.1% and S:Ni >0.5), with only minimal inclusion of
unmineralised material below mineable width.
ASX:WMG
www.westernmines.com.au
4
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
A summary of the Phase 1 RC assay results are listed below:
MTRC001
Cumulative
253m at 0.24% Ni, 128ppm Co, 76ppm Cu, 27ppb Pt+Pd with S:Ni 1.4
MTRC002
Cumulative
111m at 0.31% Ni, 136ppm Co, 69ppm Cu, 37ppb Pt+Pd with S:Ni 0.7
MTRC003
Cumulative
175m at 0.26% Ni, 114ppm Co, 18ppm Cu, 19ppb Pt+Pd with S:Ni 0.6
MTRC004
No significant mineralisation
MTRC005
Cumulative
164m at 0.26% Ni, 134ppm Co, 114ppm Cu, 20ppb Pt+Pd with S:Ni 1.3*
MTRC006
Cumulative
159m at 0.29% Ni, 125ppm Co, 29ppm Cu, 12ppb Pt+Pd with S:Ni 0.6*
MTRC007
Cumulative
168m at 0.29% Ni, 125ppm Co, 29ppm Cu, 12ppb Pt+Pd with S:Ni 1.0*
MTRC008
Cumulative
91m at 0.24% Ni, 122ppm Co, 53ppm Cu, 15ppb Pt+Pd with S:Ni 1.1
MTRC009
Cumulative
367m at 0.26% Ni, 133ppm Co, 74ppm Cu, 25ppb Pt+Pd with S:Ni 1.3
MTRC010
Cumulative
106m at 0.25% Ni, 119ppm Co, 25ppm Cu, 15ppb Pt+Pd with S:Ni 1.0
MTRC011
Cumulative
110m at 0.24% Ni, 128ppm Co, 75ppm Cu, 26ppb Pt+Pd with S:Ni 1.9
MTRC012
Cumulative
190m at 0.22% Ni, 124ppm Co, 68ppm Cu, 21ppb Pt+Pd with S:Ni 1.8
MTRC013
Cumulative
149m at 0.29% Ni, 131ppm Co, 42ppm Cu, 30ppb Pt+Pd with S:Ni 1.0
MTRC014
Cumulative
158m at 0.26% Ni, 121ppm Co, 37ppm Cu, 20ppb Pt+Pd with S:Ni 0.5
MTRC015
Cumulative
129m at 0.34% Ni, 156ppm Co, 163ppm Cu, 25ppb Pt+Pd with S:Ni 1.3
MTRC016
200m at 0.30% Ni, 139ppm Co, 92ppm Cu, 25ppb Pt+Pd from 103m S:Ni 1.2
MTRC017
Cumulative
183m at 0.26% Ni, 132ppm Co, 165ppm Cu, 16ppb Pt+Pd with S:Ni 1.6
MTRC018
Cumulative
209m at 0.28% Ni, 129ppm Co, 381ppm Cu, 18ppb Pt+Pd with S:Ni 1.3*
MTRC019
MTRC020
186m at 0.28% Ni, 135ppm Co, 78ppm Cu, 22ppb Pt+Pd from 90m S:Ni 1.2
Cumulative
220m at 0.28% Ni, 132ppm Co, 112ppm Cu, 18ppb Pt+Pd with S:Ni 1.1*
MTRC021
No significant mineralisation
MTRC022
No significant mineralisation
* Ending in mineralisation
During the quarter the Company completed a further 17 hole, 5,534m Phase 2 RC program predominantly
focus on infilling the higher grade core area identified by the Company’s JORC Exploration Target modelling
(ASX, 2024 Exploration Programs Commence at Mulga Tank, 29 January 2024; Completion of Phase 2 RC
Drilling Commencement of EIS3, 8 April 2024). The RC holes were focused around Phase 1 holes MTRC015 to
MTRC018 in the centre of the main body of the Complex, in particular around MTRC016 that returned 200m at
0.31% Ni (including 35m at 0.45% Ni) from 103m.
The drill hole spacing in this central area was reduced to approximately 200m x 200m, from the initial 500m x
300m spacing of the Phase 1 program, covering an area of around 800m x 900m. Each hole was designed to a
target depth of 300-350m, which was achieved in all holes, for a total of 5,534m - of which the top ~60m of
each hole, or 1,064m in total, was mud-rotary drilling through the sand cover.
Visible sulphide mineralisation was observed in the Phase 2 RC holes (ASX, Semi-Massive Sulphide in Mulga
Tank Phase 2 RC Holes, 29 February 2024). All holes were sampled at 1m intervals from the start of RC drilling
(i.e. base of mud rotary) with a total of 4,470 samples delivered to the ALS laboratory in Perth for geochemical
assay. Results from the first 13 holes MTRC023 to MTRC034 and MTRD038 have already been reported (ASX,
MTRC024 Assays - Matrix-Massive Sulphide over 4.5% Ni; Further RC Results with 200m Zones of
Mineralisation, 28 March 2024; MTRC032 Assays Matrix Sulphide 6m at 1.01% Ni 0.32% Cu, 10 April 2024;
MTRC038 Assay Results up to 3.16% Ni and 1.20% Cu, 16 April 2024) whilst results from the remaining four
holes are anticipated over the next few weeks.
ASX:WMG
www.westernmines.com.au
5
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
Figure 2: Phase 1 RC assay results for shallow nickel sulphide mineralisation in the Mulga Tank Complex
A summary of the Phase 2 RC assay results are listed below:
MTRC023
Cumulative
MTRC024
MTRC025
115m at 0.28% Ni, 133ppm Co, 51ppm Cu, 27ppb Pt+Pd with S:Ni 0.9
199m at 0.31% Ni, 148ppm Co, 76ppm Cu, 23ppb Pt+Pd from 161m S:Ni 1.1*
Cumulative
MTRC026
239m at 0.28% Ni, 139ppm Co, 72ppm Cu, 19ppb Pt+Pd with S:Ni 1.2*
226m at 0.28% Ni, 125ppm Co, 62ppm Cu, 15ppb Pt+Pd from 86m S:Ni 0.7
MTRC027
Cumulative
193m at 0.26% Ni, 124ppm Co, 78ppm Cu, 22ppb Pt+Pd with S:Ni 1.0*
MTRC028
Cumulative
152m at 0.30% Ni, 134ppm Co, 109ppm Cu, 20ppb Pt+Pd with S:Ni 0.9
MTRC029
Cumulative
138m at 0.25% Ni, 113ppm Co, 32ppm Cu, 6ppb Pt+Pd with S:Ni 0.6*
MTRC030
Cumulative
179m at 0.28% Ni, 126ppm Co, 41ppm Cu, 10ppb Pt+Pd with S:Ni 0.7*
MTRC031
210m at 0.28% Ni, 137ppm Co, 104ppm Cu, 24ppb Pt+Pd from 87m S:Ni 1.2
MTRC032
198m at 0.28% Ni, 145ppm Co, 249ppm Cu, 28ppb Pt+Pd from 108m S:Ni 1.6*
MTRC033
Cumulative
184m at 0.27% Ni, 126ppm Co, 82ppm Cu, 18ppb Pt+Pd with S:Ni 0.9*
MTRC034
240m at 0.30% Ni, 133ppm Co, 133ppm Cu, 36ppb Pt+Pd from 90m S:Ni 1.0*
MTRC038
199m at 0.31% Ni, 139ppm Co, 260ppm Cu, 27ppb Pt+Pd from 119m S:Ni 1.3*
* Ending in mineralisation
ASX:WMG
www.westernmines.com.au
6
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
Figure 3: Phase 2 assay results for shallow disseminated nickel sulphide mineralisation
around the core area
Broad intersections of visible disseminated nickel sulphide mineralisation, grading up to semi-massive in some
intersections, were observed and logged in the Phase 2 RC program (ASX, Semi-Massive Sulphide in Mulga
Tank Phase 2 RC Holes, 29 February 2024). These observations were confirmed by assay results with a number
of the holes returning higher grade assay results between 1% to 4.5% Ni. Relatively shallow higher grade results
within the central core area of the Mulga Tank Complex include:
MTRC015
1m at 1.11% Ni, 379ppm Co, 0.45% Cu, 62ppb Pt+Pd from 172m
3m at 1.32% Ni, 516ppm Co, 0.10% Cu, 34ppb Pt+Pd from 184m
2m at 1.71% Ni, 836ppm Co, 0.10% Cu, 0.4g/t Pt+Pd from 229m
MTRC018
1m at 1.84% Ni, 0.10% Co, 4.88% Cu, 26ppb Pt+Pd from 293m
MTRC024
1m at 1.28% Ni, 890ppm Co, 427ppm Cu, 37ppb Pt+Pd from 202m
3m at 2.19% Ni, 777ppm Co, 597ppm Cu, 9ppb Pt+Pd from 253m
inc. 1m at 4.51% Ni, 0.16% Co, 0.14% Cu, 16ppb Pt+Pd from 253m
ASX:WMG
www.westernmines.com.au
7
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
MTRC032
1m at 1.08% Ni, 602ppm Co, 379ppm Cu, 83ppb Pt+Pd from 131m
6m at 1.01% Ni, 443ppm Co, 0.32% Cu, 0.12g/t Pt+Pd from 254m
MTRC038
2m at 1.51% Ni, 539ppm Co, 0.72% Cu, 94ppb Pt+Pd from 135m
1m at 3.16% Ni, 662ppm Co, 385ppm Cu, 0.18g/t Pt+Pd from 192m
Figure 4: Higher-grade assay results over 1% Ni within the core of the Mulga Tank Ultramafic Complex
JORC EXPLORATION TARGET
Modelling of all the Company’s Phase 1 RC and 2023 diamond drilling results identified a significant zone of
shallow disseminated nickel sulphide mineralisation in the main body of the Mulga Tank Complex. The Company
completed implicit grade modelling of these results, using an industry standard 3D geological modelling
software package, and reported Exploration Target in accordance with JORC 2012 (ASX, Mulga Tank JORC
Exploration Target, 5 February 2024). The Company’s internal modelling work was reviewed by independent
consultants CSA Global. The Exploration Target with an estimated range of potential mineralisation is:
ASX:WMG
www.westernmines.com.au
8
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
350 to 2,200 million tonnes grading 0.24% to 0.35% Ni, 120 to 150ppm Co with S:Ni 1.1 to 1.3
SUMMARY OF RELEVANT EXPLORATION DATA
Since listing in July 2021 WMG has undertaken a series of exploration programs at the Mulga Tank Project
which were included in the Exploration Target modelling:
17 diamond drill holes totalling 11,712.8m
22 reverse circulation (RC) drill holes totalling 7,035.5m
15,115 drill hole assay samples
20,525 diamond core pXRF measurements
In addition, historical exploration at the Mulga Tank project has included 12 diamond drill holes totalling
4,399.4m. These drill holes have been included in the project database when looking at the geological
interpretation of the Complex and dimensions of the dunite intrusion but generally excluded from the implicit
geochemical modelling of mineralisation as the various historical assay suites often lacked elements WMG
considers critical to the interpretation, such as sulphur (S), and/or the historical drill holes fell outside the area
investigated by the modelling.
The Company focused its modelling work over an approximate 3.5km x 1.9km area in the centre of the main
body of the Mulga Tank Complex. The relevant WMG drill holes from the project database used in the modelling
are shown in Figure 5 below:
Figure 5: Plan view of area of investigation and drill holes used in implicit modelling
ASX:WMG
www.westernmines.com.au
9
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
LARGE VOLUME LOWER GRADE MODEL
To construct a large volume/lower grade range estimate for the Exploration Target range a shallow mineralised
volume was modelled based on a nickel cut-off of >0.15% Ni, coincident with a sulphur cut-off of >0.1% S,
between 380mRL and 100mRL (Figure 6).
W
E
Outer shell
of dunite body
Figure 6: Implicit modelling of mineralised volume using coincident >0.15% Ni and 0.1% S cut-offs
Outline of main Mulga Tank dunite body, viewed from south looking north
In the centre of the target area a medium-grade mineralised volume was modelled based on a nickel cut-off of
>0.20% Ni, coincident with a S:Ni ratio of >0.5, between 380mRL and -100mRL (Figure 7).
W
E
Outer shell
of dunite body
Figure 7: Implicit modelling of mineralised volume using coincident >0.20% Ni and >0.5 S:Ni cut-offs
Outline of main Mulga Tank dunite body, viewed from south looking north
ASX:WMG
www.westernmines.com.au
10
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
These mineralised volumes were combined to construct the large volume/lower grade estimate for the
Exploration Target (Figure 8).
W
E
Outer shell
of dunite body
Figure 8: Combined mineralised volume for Large Volume/Lower Grade Exploration Target estimate
Outline of main Mulga Tank dunite body, viewed from south looking north
SMALLER VOLUME HIGHER GRADE MODEL
To construct a smaller volume/higher-grade estimate for the Exploration Target range a higher-grade mineralised
volume was modelled based on a nickel cut-off of >0.28% Ni, predominantly associated with the area around
holes MTRC015 and MTRC016 and allowing for some projection of these results (Figure 9). This modelling was
limited to a depth range of 380m RL to -100m RL and also excluded other zones above 0.28% Ni outside this
central area.
W
E
Outer shell
of dunite body
ASX:WMG
Figure 9: Implicit modelling of mineralised volume using >0.28% Ni
Outline of main Mulga Tank dunite body, viewed from south looking north
www.westernmines.com.au
11
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
SUMMARY OF VOLUME GRADE REPORTS
Volume/tonnage and average grades were estimated for each of the scenarios modelled and used to produce
end members for the estimated range of potential mineralisation reported as the Exploration Target (Table 1,
Figure 10):
Estimate Range
Cut-offs
Tonnes
Ni (%)
S (ppm)
Co (ppm)
S:Ni
Shallow large volume/lower grade
1,500 Ni, 1,000ppm S
1,800Mt
0.24
3,092
122
1.3
Deeper medium volume/lower grade
2,000 Ni, 0.5 S:Ni
1,000Mt
0.27
3,529
133
1.3
Combined large volume/lower grade
estimate end member
Combined
2,200Mt
0.24
3,092
123
1.3
Smaller volume/higher grade
estimate end member
2,800ppm Ni
350Mt
0.35
3,700
146
1.1
Table 1: Summary of range of Exploration Target scenario estimates
The results have been reported as an Exploration Target with an estimated range of potential mineralisation of:
350 to 2,200 Million Tonnes grading 0.24% to 0.35% Ni, 120 to 150ppm Co with S:Ni 1.1 to 1.3
W
E
Outer shell
of dunite body
Figure 10: Mineralised volumes defined for the range of Exploration Target estimates
(pink = large volume, low grade; red = small volume, high grade)
Outline of main Mulga Tank dunite body, viewed from south looking north
ASX:WMG
www.westernmines.com.au
12
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
DISCUSSION
Another great quarter and a great start to 2024 for the Company. Drilling to date at the project highlights an
extensive magmatic nickel sulphide mineral system within the Mulga Tank Ultramafic Complex, with visible nickel
sulphide encountered nearly everywhere we drill. Significant Type 2 Mt Keith-style disseminated nickel sulphide
mineralisation has been demonstrated across the majority of the main body of the Complex, some ~4km.
The 22 RC hole program completed at the end of 2023, covering an area of approximately 2,500m x 1,000m,
was very successful in confirming the continuity of the broad intervals of shallow disseminated nickel sulphide
mineralisation, within the top 300 vertical metres.
This zone of shallow Mt Keith-style mineralisation could be amenable to large scale open pit mining, which the
Company reported as an Exploration Target in early February. This was a major milestone for both the project
and the Company; a culmination of two years of steadily improving results at the project. The Exploration Target
highlights Mulga Tank could be a potentially globally significant nickel sulphide deposit.
In follow-up to the Exploration Target modelling the Company focused the Phase 2 RC program on the higher
grade core area, looking to infill, improve confidence, progressively de-risk and aid resource evaluation of this
zone. The Phase 2 geochemical assays received so far have included some standout results with multiple holes
demonstrating mineralised intervals greater than 200m length, repeating the result of Phase 1 hole MTRC016.
Whilst the Company continues to de-risk the extensive shallow disseminated mineralisation, there is increasing
evidence of a likely Type 1/2 hybrid nickel sulphide mineral system more akin to Perseverance-style
mineralisation (basal massive sulphide component). This includes numerous examples of remobilised massive
sulphide veinlets and visible larger in-situ immiscible sulphide globules seen in diamond drilling throughout the
Complex.
Visible sulphides grading up to semi-massive in some intersections, were observed and logged in the Phase 2
RC program. These were confirmed by geochemical assay results with a number of the holes returning higher
grade assay results between 1% to 4.5% Ni, in relatively shallow intersections. These results are distributed
across the central area of the Complex, some of which can start to be correlated between drill holes over
several hundreds of metres. The Company will look to target thicker intervals of this material with follow-up work
- just a modest improvement in the width of these high grade intersections could really change the value
proposition of the project.
ASX:WMG
www.westernmines.com.au
13
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
JASPER HILL
The Jasper Hill Project comprises exploration licences E39/2073, E39/2079 and prospecting licence application
P39/6267. The project is located approximately 80km southeast of Laverton and covers part of the poorly
exposed Merolia Greenstone Belt, a NNW trending belt, up to 20km wide, that can be traced over 110km in a
SSE direction from the Burtville Mining Centre. The project area is lightly explored, due to being partly under
shallow cover, but is contiguous to the historical producing mines of Lord Byron (160,000oz at 1.0g/t Au) and
Fish (87,000oz at 4.1g/t Au).
Jasper Hill is the Company’s primary gold project containing a mineralised gold trend over 3km strike. The
Company as completed field reconnaissance work involving geological mapping, high-resolution ground
magnetic survey and locating historical drill collars significant aboriginal heritage sites. The Company plans to
complete a litho-structural interpretation and drill targeting work, to advance the project ready for an initial RC
drilling program.
During the previous period the Company reached agreement on industry standard access agreements with
neighbouring miscellaneous licence holders in order to proceed with the grant of prospecting licence application
P39/6267 and standardise access agreements across the project area.
Figure 11: WMG ground magnetic survey and significant historical drill intersections (E39/2073 and P39/6267)
ASX:WMG
www.westernmines.com.au
14
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
During the quarter the Company completed a desktop review of the project and made plans for initial fieldwork
campaigns involving ground magnetic (extending current coverage) and ground gravity surveys for the current
period.
YOUANMI
The Youanmi Project comprises exploration licence E57/1119. The project is located 70km southwest of
Sandstone and lies on the eastern side of the Youanmi Greenstone Belt, along the major Youanmi Shear.
The tenement is located 7km from the historic Youanmi Gold Mining Centre, which has produced over
600,000oz of gold since its discovery in the late 1800’s, currently owned by Rox Resources (ASX:RXL) and
Venus Metals (ASX:VMC). The area has seen a resurgence in exploration activity with the recent discovery of the
high-grade Penny North (ASX:RMS) and Grace (ASX:RXL) deposits along the Youanmi Shear.
A site visit for field reconnaissance and part of a high-resolution ground magnetic survey were completed during
2023. Following a review of the project and identification of the historical Deep Well prospect the Company
undertook further fieldwork during the quarter involving ground gravity surveying.
Figure 12: Historical Deep Well RAB drilling and WMG ground gravity survey points
ASX:WMG
www.westernmines.com.au
15
ASX RELEASE | QUARTERLY ACTIVITIES REPORT MARCH 2024
MELITA
The Melita Project comprises exploration licence E40/379, covering an area of approximately 105km2. The
project is located 20km south-southeast of Leonora and to the north of the Kookynie, Niagara and Orient WellButterfly gold mining centres, in the heart of the WA Goldfields. The Kookynie area has seen recent upswing in
exploration, with WMG’s Melita Project surrounded by the likes of Genesis Minerals (ASX:GMD), Saturn Metals
(ASX:STN), Azure Minerals (ASX:AZS), KIN Mining (ASX:KIN) and .
The Company notes the increase in M&A activity around the Leonora-Kookynie area and undertook a review of
the project, including soil geochemical and ground magnetic data collected during a series of WMG field
campaigns (ASX, Major Field Program Commences at Melita, 11 August 2021; Completion of Initial Field
Program at Melita, 16 September 2021).
During the quarter the Company completed a field visit to the Melita Project. A high resolution ground gravity
survey was completed over the Airstrip Gossan area, along with geological mapping and sampling. A number of
additional outcrops of Cu-Pb-Zn gossans were identified and sampled. At the Princess Melita area additional
geological mapping of historical workings, sampling and metal detecting was undertaken.
Figure 13: Technical Director Dr Ben Grguric examining historical gold workings at the Melita Project