Western Mines Group Ltd (WMG or Company) (ASX:WMG) is pleased to update shareholders on the progress
of exploration activities at the Mulga Tank Ni-Cu-Co-PGE Project, on the Minigwal Greenstone Belt, in Western
Australia’s Eastern Goldfields.
Having recently completed a capital raise (ASX, Significant Capital Raise to Advance Mulga Tank, 14 October
2025) the Company is a strong position to finish the current Phase 4 drilling program (ASX, Exploration Drilling to
Recommence at Mulga Tank, 30 June 2025) and continue further drilling well into the first half of 2026. Planned
holes between now and the end of the year include deep diamond hole EIS9 and nine reverse circulation (RC)
holes looking to infill and expand the current Mineral Resource Estimate. Deep diamond hole EIS9 will utilise one
of our three successful Exploration Incentive Scheme (EIS) grants, which cumulatively total $620,000 of co-
funded drilling (ASX, WMG Wins Two EIS Awards Totalling $440,000 for Mulga Tank, 28 April 2025; WMG Wins
EIS Award to Drill Komatiite Targets at Mulga Tank, 10 October 2025).
In addition to the drilling, a Moving Loop ElectroMagnetic (MLEM) survey is planned to commence in mid-
November. The survey will look to extend existing coverage over the Panhandle area of the project, in particular
testing the mineralised komatiite body in tenement E39/2134. Results from the survey will be used to aid
targeting of seven EIS co-funded RC and diamond drill holes available to be drilled in early 2026.
ASX:WMG www.westernmines.com.au 1
Western Mines Group Ltd
Unit 10, 448 Roberts Road
Subiaco WA 6008
HIGHLIGHTS
• Update on Phase 4 exploration drilling at the Mulga Tank Ni-Co-Cu-PGE Project
• Company has completed first half of the Phase 4 RC program including:
MTRC064 to MTRC067 - 4 x RC holes in the main body of the Mulga Tank Complex
MTRC063 diamond tail - testing Panhandle komatiite system
MTD030 (EIS8) - first stratigraphic hole through the Panhandle komatiite system
MTRC011 diamond tail - first hole testing basal zone along western margin of the Complex
MTRC055 diamond tail - extending higher-grade RC hole as DHEM conduit
• Further drilling planned through to the end of the year includes:
MTRC009 (EIS9) diamond tail - EIS deep diamond hole testing basal zone of the Complex
MTRC068 to MTRC076 - 9 x RC holes infilling resource in the main body Complex
• MLEM survey extending over the Panhandle komatiite system planned for November
• Ongoing exploration modelling, targeting work and the results of the MLEM/DHEM surveys will
add further drill holes in early 2026 including maximising $620,000 of available EIS grants
COMMENCING EIS9 AND PHASE 4 DRILLING UPDATE
ASX RELEASE
10 NOVEMBER 2025
Telephone: +61 475 116 798
Email: contact@westernmines.com.au
Shares on Issue: 113.75m
Share Price: $0.215
Market Cap: $24.46m
Cash: $3.99m (31/10/25)
Commenting on the exploration plans, WMG Managing Director Dr Caedmon Marriott said:
“After the recent capital raise, and a brief break, the team are back on site for further drilling at the
Mulga Tank Project. We have ten holes we hope to drill between now and Christmas, including
deep diamond hole EIS9, and we’re already starting to plan our activities for next year.
Co-funded deep diamond hole EIS9 will look to further test the active basal zone of the Complex,
searching for a sulphide enriched keel. We’ve moved the hole from a previous position and will now
target a coincident magnetic high feature and conductive MobileMT anomaly sitting in a hinge
position at the base of the western margin. We think we can drill this as a diamond tail off previous
RC hole MTRC009, saving time and some ~520m of drilling.
Three infill RC holes are planned between the two zones of Indicated Resource and a further six
holes are planned to south of the current resource, extending towards the first four RC holes of
Phase 4 program. Mud-rotary pre-collars of these holes are currently being drilled, with the hope
that a second RC rig will be available between now and Christmas to complete the RC component
- which should take about 10-12 days.
Finally, a high-powered MLEM survey is planned for the last two weeks of November, to extend our
previous 2021-22 survey over the mineralised komatiite system in tenement E39/2134. Results
from this survey will be used to aid targeting of seven co-funded EIS holes to be drilled in 2026.”
MULGA TANK EXPLORATION PROGRAMS
Exploration results from the Company’s various drilling programs at the Mulga Tank Project over the last three
years have demonstrated significant nickel sulphide mineralisation and an extensive nickel sulphide mineral
system within the Mulga Tank Ultramafic Complex.
WMG has undertaken a combination of both diamond and reverse circulation (RC) drilling. With this two
pronged approach, RC is used to infill and prove up the extent of shallow disseminated nickel sulphide
mineralisation, defined by the Company’s Mineral Resource Estimate (ASX, Mulga Tank Mineral Resource Over
5Mt Contained Nickel, 10 April 2025), whilst the diamond drilling program continues to test deeper targets for
basal massive sulphide.
The Company has planned a combination of both further RC and diamond drilling, funded by our recent capital
raise and multiple successful EIS grants.
PHASE 4 RC DRILLING
The Company completed four RC holes (MTRC064 to MTRC067) at the start of the Phase 4 program back in
early August. These holes were designed to step-out approximately 300m to the south of previous drilling, with
the holes fairly wide spaced at ~400m intervals along and E-W fence. All four holes encountered broad intervals
of visible disseminated sulphide mineralisation, with some occurrences of coarser sulphide. Visual observations
were confirmed by subsequent assay results, successfully extending known mineralisation outside the current
Mineral Resource shell (ASX, First Phase 4 RC Holes Complete at Mulga Tank, 4 August 2025; MTCR066 Best
RC Hole to Date at Mulga Tank, 18 September 2025).
ASX:WMG www.westernmines.com.au 2
ASX RELEASE | COMMENCING EIS9 AND PHASE 4 DRILLING UPDATE
The team is currently mud-rotary pre-collaring nine further RC holes within the main body of the Complex (Figure
1). Three of these will infill between the two areas of Indicated Mineral Resource, to reduce drill spacing and
increase resource confidence, hoping to linkup these two areas. A further six holes are planned between the
current resource shell and the first Phase 4 step-out fence, hoping to extend the current mineral resource. Three
of these holes to the north of hole MTRC066 are of particular interest, with hole MTRC066 being one of the best
mineralised shallow RC holes ever drilled at the project (ASX, MTCR066 Best RC Hole to Date at Mulga Tank,
18 September 2025).
EIS9 DEEP DIAMOND HOLE
Following the completion of mud-rotary pre-collaring the RC holes the Company will commence deep diamond
hole EIS9. The Company was successful in its EIS Deep Drilling application in previous Round 31 of the Co-
funded Exploration Drilling Program for a further deep diamond hole within the main body of the Mulga Tank
Complex (ASX, WMG Wins Two EIS Awards Totalling $440,000 for Mulga Tank, 28 April 2025). The Company’s
exploration thesis and significant evidence to date suggested the very active basal zone of the Complex could
likely host Perseverance-style high-grade deposits. This hole is another opportunity to test for a high-grade
sulphide enriched keel.
ASX:WMG www.westernmines.com.au 3
Figure 1: Phase 4 Planned Drill Holes
ASX RELEASE | COMMENCING EIS9 AND PHASE 4 DRILLING UPDATE
Diamond drilling at Mulga Tank has demonstrated the extensive presence of intercumulus sulphide blebs
(predominantly pentlandite), localised at the interstices between former olivine crystals, characteristic of Type 2
disseminated nickel sulphide systems and exemplified by the Mount Keith deposit. Within the basal zone of the
Complex numerous intersections of thin (<20cm) high-tenor massive sulphide veins, large immiscible sulphide
globules and high-grade sulphide segregations have been encountered. With further occurrences in this zone
seen in recent diamond tail MTRC011 (ASX, High-Grade Sulphide Segregations at Depth in MTRC011, 30
October 2025).
The presence of both these types of mineralisation is evidence that Mulga Tank represents a so-called Hybrid
system, in which both cotectic precipitation and gravity settling of sulphides has occurred. This markedly
increases the prospectivity of the system, allowing for possible significant basal accumulations of massive and
matrix sulphide.
The extensive sulphide system throughout the intrusion, and the active basal zone delineated over ~2km across
the intrusion floor, suggests the entire Mulga Tank Complex sits in a very prospective “textbook” proximal
position to an upwelling magma vent (Figure 3 schematic figure from Fiorentini et al., 2012).
EIS9 will look to target a magnetic high feature, from 3D magnetic inversion, coincident with a conductive
MobileMT anomaly within the basal zone of the Complex. This feature sits in a possible fold hinge position at the
base of the western margin. The hole will test a new area within the basal zone which is located between
intersections of high-grade sulphide segregations to the WNW in holes MTD028 and MTRC011 tail and also to
the east in hole MTD029 (EIS3).
The hole will be drilled as a diamond tail from Phase 1 RC hole MTRC009, saving over 500m of diamond drilling.
MTRC009 was drilled to 522m, the deepest RC hole drilled in Australia by Blue Spec Drilling, and encountered
~390m of visible disseminated sulphide mineralisation confirmed by geochemical assays returning cumulative
367m at 0.26%, 133ppm Co, 74ppm Cu, 25ppb Pt+Pd with S:Ni 1.3.
ASX:WMG www.westernmines.com.au 4
Figure 2: EIS9 targeting 3D magnetic high and conductivity MobileMT anomaly in hinge zone at base of
western margin
ASX RELEASE | COMMENCING EIS9 AND PHASE 4 DRILLING UPDATE
ASX:WMG www.westernmines.com.au 5
EIS9
Figure 3: Schematic figure of “camp-scale” nickel sulphide
occurrences within the Agnew-Wiluna Belt, WA
Figure 4: 3D magnetic inversion image of the Mulga Tank Complex with schematic magma flow direction.
Location of EI9 further targeting basal zone looking for massive sulphide accumulation close to feeder vent.
ASX RELEASE | COMMENCING EIS9 AND PHASE 4 DRILLING UPDATE
Inferred upwelling magma vent
3D magnetic inversion model
MLEM SURVEY EXTENSION
In conjunction with the ongoing drilling, a Moving Loop ElectroMagnetic (MLEM) survey is also planned to
commence in mid-November. The high-powered, low frequency survey will look to extend existing coverage
over the Panhandle area of the project at 200m line spacing. The survey is focused on the mineralised komatiite
body in tenement E39/2134 and aims to detect bedrock conductors that could represent nickel sulphide
mineralisation. Results from the survey will be used to aid targeting of seven EIS co-funded RC and diamond
drill holes available to be drilled in early 2026.
ASX:WMG www.westernmines.com.au 6
Figure 5: Planned MLEM Survey Lines November 2025
ASX RELEASE | COMMENCING EIS9 AND PHASE 4 DRILLING UPDATE
EIS Round Award Valid Tenement Drill Type Comments
R31 $220,000 1/6/25 to 31/5/26 E39/2132 Deep diamond
1 x deep diamond hole >1,000m within main Complex
EIS9 commencing this week
R31 $220,000 1/6/25 to 31/5/26 E39/2134 Deep diamond
2 x deep diamond holes >700m within the Panhandle
magnetic feature - first hole MTD030 (EIS8) drillied
R32 $180,000 1/12/25 to 30/11/26 E39/2134 RC/diamond
6 x RC holes (two with diamond tails) within the
Panhandle magnetic feature
Table 1: Current WMG EIS grants at Mulga Tank
The Company is pleased to present plans for the next phase of drilling and exploration activities and looks
forward to updating shareholders on the continuing progress at Mulga Tank as results are received.
For further information please contact: Dr Caedmon Marriott
Managing Director
Tel: +61 475 116 798
Email: contact@westernmines.com.au
Papers referenced:
District to Camp Controls on the Genesis of Komatiite-Hosted Nickel Sulfide Deposits, Agnew-Wiluna Greenstone Belt,
Western Australia: Insights from the Multiple Sulfur Isotopes; M. Fiorentini et al., 2012; Economic Geology v. 107, pp
781-796
ASX:WMG www.westernmines.com.au 7
This announcement has been authorised for release to the ASX by Dr Caedmon Marriott, Managing Director
ASX RELEASE | COMMENCING EIS9 AND PHASE 4 DRILLING UPDATE
Item November December
E39/2132
Rotary pre-collar 9 RC holes
Deep diamond hole EIS9
9 RC holes infill and extension
E39/2134
MLEM survey
Table 2: Planned activities at Mulga Tank before year end
ASX:WMG www.westernmines.com.au 8
ABOUT WMG
Western Mines Group Ltd (ASX:WMG) is a mineral exploration company driven by the goal
to create significant investment returns for our shareholders through exploration and
discovery of high-value gold and nickel sulphide deposits across a portfolio of highly-
prospective projects located on major mineral belts of Western Australia.
Our flagship project is the Mulga Tank Ni-Co-Cu-PGE Project, a major ultramafic complex
found on the under-explored Minigwal Greenstone Belt (100% WMG). WMG’s exploration
work has discovered a significant nickel sulphide mineral system and is considered highly
prospective for globally significant Ni-Co-Cu-PGE deposits. An Mineral Resource Estimate
of 1,968Mt at 0.27% Ni, over 5.3Mt of contained nickel, was announced in April 2025,
making Mulga Tank the largest nickel sulphide deposit in Australia.
The Company’s primary gold project is Jasper Hill, where WMG has strategically
consolidated a 3km mineralised gold trend with walk-up drill targets. WMG has a diversified
portfolio of other projects including Melita (Au, Cu-Pb-Zn), midway between Kookynie and
Leonora in the heart of the WA Goldfields; Youanmi (Au) and Pinyalling (Au, Cu, Li).
COMPETENT PERSONS STATEMENT
The information in this announcement that relates to Exploration Results and other technical
information complies with the 2012 Edition of the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves (JORC Code) and has been
compiled and assessed under the supervision of Dr Caedmon Marriott, Managing Director
of Western Mines Group Ltd. Caedmon is a Member of the Australian Institute of
Geoscientists and a Member of the Society of Economic Geologists. He has sufficient
experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the JORC Code. Caedmon consents to the inclusion in this
announcement of the matters based on his information in the form and context in which it
appears.
DISCLAIMER
Some of the statements appearing in this announcement may be in the nature of forward looking statements. You should be
aware that such statements are only predictions and are subject to inherent risks and uncertainties. Those risks and
uncertainties include factors and risks specific to the industries in which WMG operates and proposes to operate as well as
general economic conditions, prevailing exchange rates and interest rates and conditions in the financial markets, among
other things. Actual events or results may differ materially from the events or results expressed or implied in any forward
looking statement. No forward looking statement is a guarantee or representation as to future performance or any other
future matters, which will be influenced by a number of factors and subject to various uncertainties and contingencies, many
of which will be outside WMG’s control.
WMG does not undertake any obligation to update publicly or release any revisions to these forward looking statements to
reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events. No representation or
warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions
or conclusions contained in this announcement. To the maximum extent permitted by law, none of WMG, its Directors,
employees, advisors or agents, nor any other person, accepts any liability for any loss arising from the use of the information
contained in this announcement. You are cautioned not to place undue reliance on any forward looking statement. The
forward looking statements in this announcement reflect views held only as at the date of this announcement.
Western Mines Group Ltd
ACN 640 738 834
Unit 10, 448 Roberts Road
Subiaco
WA 6008
Board
Rex Turkington
Non-Executive Chairman
Dr Caedmon Marriott
Managing Director
Francesco Cannavo
Non-Executive Director
Dr Benjamin Grguric
Technical Director
Capital Structure
Shares: 113.75m
Options: 16.65m
Share Price: $0.215
Market Cap: $24.46m
Cash (31/10/25): $3.99m
Follow us
@westernmines
Western Mines Group
ASX RELEASE | COMMENCING EIS9 AND PHASE 4 DRILLING UPDATE
Share your feedback
Discover